2011 Changes
to Mechanics' Liens
New Mechanics’ Lien Laws 2011 – What you don’t
know WILL hurt you
Starting January 1, 2011 the newly amended mechanics’
lien laws will take effect. These new laws provide more protection
to the property owners when a lien is placed on their property,
and the new laws impose strict timelines for notification of
liens. If you forget or ignore the new changes, you will lose
your mechanics’ lien rights. Is it too soon to start thinking
about these important changes to the laws? To put it simply
- no. It’s better to start thinking about them now, rather
than kicking yourself later for not understanding them and putting
safeguards into to your procedures to ensure compliance.
As any well informed contractor or supplier already knows,
the California Constitution gives you the right to a mechanic’s
lien for the value of labor and materials provided for the improvement
of real property. Legislature is authorized to provide for the
speedy and efficient enforcement of these liens, which leads
to the laws regulating notices (such as the requirement for
a 20-day preliminary notice) and timing to enforce your rights.
As a backdrop to looking at what has changed, let’s quickly
look at the mechanics’ lien process. In a nutshell, this
is how it works:
1. You are hired to provide work or services on a project;
2. You didn’t get paid for that work;
3. You record a mechanic’s lien against the property to
act as security for the work you provided;
4. You have to file suit to “foreclose” on the mechanic’s
lien, which can ultimately lead to a forced sale of the property
to obtain payment for your work.
Now for some critical procedural details:
First, what hasn’t changed in the mechanic’s lien
procedures:
• You must have the right to use a mechanic’s lien.
If the work you did was not consumed in the improvement, or
used to improve the property you won’t have a right to
a mechanic’s lien. If your contractor’s license
in not in strict compliance with the Contractors State License
Law, your rights to a mechanic’s lien may be impacted.
• You still need to provide a 20-preliminary notice to
the owner, the lender and the general contractor within 20 days
of first providing labor, services or materials to the site.
• Once you have completed your work on the project and
you are owed payment, you still have to record the mechanic’s
lien at the county recorder’s office in the county in
which the work was performed within the strict time frames required.
• The necessary information required on the recorded
lien has not changed, and is as follows:
1. A statement of the claimant's demand after deducting all
just credits and offsets.
2. The name of the owner or reputed owner, if known.
3. A general statement of the kind of labor, services, equipment,
or materials furnished by the claimant.
4. The name of the person by whom the claimant was employed
or to whom the claimant furnished the labor, services, equipment,
or materials.
5. A description of the site sufficient for identification.
• Once the mechanics lien has been recorded, the next
step is to file suit to foreclose on the lien (within 90 days
of recording the lien) in Superior Court in the county in which
the property is located.
Now, what has changed with this process?
• Prior to recording the mechanic’s lien, Civil
Code, Section 3084 now requires that the mechanic’s lien
as well as a “Notice of Mechanic’s Lien” be
served on the owner, or if unable to do so, then on the lender
or the general contractor. (See below for required wording of
the notice). Failure to serve the mechanic’s lien with
the required Notice of Mechanic’s Lien, shall cause the
mechanic’s lien to be unenforceable as a matter of law.
• A “proof of service affidavit” is required
to be recorded with the mechanic’s lien to prove that
service of the lien and Notice was made. Generally, service
must be done by registered mail, certified mail, or first-class
mail, evidenced by a certificate of mailing, postage prepaid.
No longer is a courtesy copy sent from the county recorder’s
office going to be good enough to put the owner on notice.
• Also, there is a change to Civil Code, Section 3146,
which applies once a lawsuit to foreclose has been filed in
Superior Court. A lis pendens (notice of pendency of action)
must be recorded with the county recorder within 20 days of
filing the foreclosure lawsuit. Previously, recording a lis
pendens was not absolutely required and the failure to record
one really only caused problems if the property was transferred
after the foreclosure lawsuit was filed. Now, now it is mandatory,
along with a recording deadline.
As mentioned above, the Notice of Mechanic’s lien must
state the following, and must be printed in at least 10-point
boldface type. The last sentence must be in uppercase type and
the exact wording must be used:
NOTICE OF MECHANIC’S LIEN
ATTENTION!
Upon the recording of the enclosed MECHANIC’S LIEN with
the county recorder’s office of the county where the property
is located, your property is subject to the filing of a legal
action seeking a court-ordered foreclosure sale of the real
property on which the lien has been recorded. That legal action
must be filed with the court no later than 90 days after the
date the mechanic’s lien is recorded.
The party identified in the mechanic’s lien may have provided
labor or materials for improvements to your property and may
not have been paid for these items. You are receiving this notice
because it is a required step in filing a mechanic’s lien
foreclosure action against your property. The foreclosure action
will seek a sale of your property in order to pay for unpaid
labor, materials, or improvements provided to your property.
This may affect your ability to borrow against, refinance, or
sell the property until the mechanic’s lien is released.
BECAUSE THE LIEN AFFECTS YOUR PROPERTY, YOU MAY WISH TO SPEAK
WITH YOUR CONTRACTOR IMMEDIATELY, OR CONTACT AN ATTORNEY, OR
FOR MORE INFORMATION ON MECHANIC’S LIENS GO TO THE CONTRACTORS’
STATE LICENSE BOARD WEB SITE AT www.cslb.ca.gov.
In summary, the main changes are
(1) the requirement for service of both the mechanic’s
lien and the notice of the lien prior to recording the lien
and
(2) the mandatory requirement of a lis pendens
to be recorded within 20 days of filing the foreclosure lawsuit.
Because many contractors and suppliers take it
upon themselves to record their own mechanics’ liens,
it is advised to put a written process in place so that none
of these critical requirements are missed.
We are...
Anything But Typical
Call us now to discuss how you can benefit by
using a different approach to managing to your legal needs.
619-544-0086
info@construction-laws.com |